Landslide Repair
Sycamore Landslide

Legal Notes

Progress Report

November 8, 2009

Landslide Repair Foundation is pleased to report that the emerging hillside looks very neat – tidy, as we see Phases I and II completed. But if one could see a hundred feet into the ground one would be absolutely amazed at the amount, substance and quality of the work that has gone on.

Phase III. 
The 31 shear pins that make up Phase III have been drilled, the reinforcing cages set, and the concrete poured. This phase is now ready for the construction of its tie beam. The greatest challenge in this Phase has been the limited space within which to work, because of the steep hillside and the relative nearness of the residences below. Work has progressed rapidly.

The tops of the poured shear pins can be seen in the attached photo. At the lower left one sees a blue panel. Just above and to the left of that panel one sees the orderly layout of the shear pin array for the Phase III wall, as it stretches toward a palm tree and beyond and awaits the installation of the tie beam, next up. Tie-backs have already been installed.

Phase VI. 
We are also working on Phase VI. A map depicting the relationships between the phases is attached. A chart depicting the relationships between the phases is seen below.

There are 39 shear pins in the first (upper) row, and 40 in the lower. The shear pins will be connected by a tie beam and up to 6 rows of tiebacks securing the shear pin-tie beam layout. A chart depicting the relationships between the phases is seen below."

Here is Condon-Johnson’s update for Phase VI, Wall 1 as of November 3, 2009:

"Two shear pins remain to be installed. We anticipate completing them on November 4, 2009. The grade beam rebar install commenced prior and is completed to approx 40% of the length and continues to be installed. We will form and pour the beam in three sections. The first section is scheduled to pour this Thursday, November 5, 2009 (Friday at the latest). A similar section will be poured the following Wednesday, November 11, 2009, or Thursday. The last section will follow 4 or 5 days later November 16-17. Tie backs are scheduled to begin at the first section Wednesday/Thursday, November 11, 2009."

Landslide Repair Foundation is very excited about this progress. See the map that follows. The location of the two walls of Phase VI is indicated in brown.

See the photo below, taken on or about October 30, from across Sycamore Canyon on Las Alturas Road. The crane being used to drill for the shear pins (white, located just to the right of center) is positioned to begin work on what is approximately shear pin #22-24, working left to right, of the 39 shear pins involved in this first wall. Wall #2 of Phase VI, will be similarly constructed and will have 40 shear pins.

See also, however, the completed work at the Halstead and Sneddon properties located upper center. These residences are being re-landscaped, with a view toward protection from the rains that will inevitably come.

Just to the right and above the crane on the slope, is where the site office is now located (on what was the former building pad for the McKenna property, the house having been destroyed by the original slide.).

Particular attention invited to how the keystone wall outlines Canon View Road, and to the keystone retaining walls above on the Halstead property; a view that is a vast aesthetic improvement over the pre-landslide layout. See also the photos in the progress report on the website.

Phase IV and V. 
Phases IV and V were deferred in favor of Phase VI, which is now under construction. These phases are still in development, and will address issues at the lower elevation of the slide area. We expect to see completed planning around mid-to-late December, 2009.  

Phase VII. 
Our effort to date has pretty much by-passed planning for Phase VII. Phase VII is generally a clean-up phase where we will address issues of landscaping, road maintenance and repair, sewer, and demobilization.

With regard to landscaping, we will be striving for plantings that are generally native, or are generally accepted plantings in our area and otherwise enhance the aesthetic appearance of the work area. We would like to see a native hillside, but one that is not cluttered by overgrowth and weeds and is not a transient hotel or home for bedding coyotes. How it stands up over time will depend entirely on what maintenance plan is set in place and who is responsible for such maintenance.

Landslide Repair Foundation has not, as of this time, retained a consulting arborist, and probably will not for some months to come. We have no idea whatsoever about what may become of the McKenna property; that will be up to the owner after we are finished. Also, the sewer and paving issues may drive our budget. We can only wait and hope in that regard.

How the LRF properties (formerly Loberg and Peyton) will be used has never really been addressed by the board of directors or others. Those properties will probably not be developed for many years to come, if ever, because of the subterranean improvements that have been installed and/or the need for City or County permitting.

Eventually, "as-built" drawings will be available to any inquiring party as they will be recorded in City/County records.




 

See additional progress reports:


See progress photo galleries

 

 

 

                        

©2007-2011 Landslide Repair Foundation, Inc.