Landslide Repair
Sycamore Landslide

Legal Notes

Project Details > Time Table


The current time table for completion of work on the project is as depicted in the chart below.  However, all dates in the table are subject to review and revision as the needs of the project develop.  Neither Landslide Repair Foundation nor its advisors guarantee strict adherence to the dates indicated below.  These dates will be updated for review on this website as the need for change develops. 

 

Phase

Description

Start
Construction(*)

Complete Construction

I

Arrest Upslope Expansion

1/15/2008

1/30/2009

II

Restore Upper Roads

6/15/2008

7/31/2009

III

Pin Incipient Landslide

7/1/2009

11/30/2009

IV

Protect Lower Roads (**)

4/15/2010

4/30/2011

V

Buttress Landslide with Fill (**)

4/15/2010

4/30/2011

VI

Pin Landslide Body

8/15/2009

11/30/10

VII

Landscape & Repave Roads

10/15/2010

8/31/2011

(*)  All dates effective 7/25/2009 and until superseded or changed by conditions at the worksite.
(**) Phases IV & V will follow completion of Phase VI, due to reevaluation of conditions onsite.

 